Case Study

Paste Fill Hole Reaches 2,152 ft in a One-Shot Pass

At Paulsens Gold Mine, Boart Longyear drilled a 656 m paste fill hole in one pass, reaching the target in 39 shifts and intersecting within 2.1 m of center.

Service
Directional Drilling
Region
Australia
Application
Paste Fill Drilling
Project type
Mining
The 656 m hole reached the target in 39 12-hour shifts and intersected approximately 2.1 m from target center.

Executive snapshot

Client
Northern Star Resources
Service Used
Directional Drilling
Operating Environment
Active gold mine
Project Outcome
656 m / 39 shifts

Project Requirements

What the project required

Project Conditions

A 310 mm bore was required so the full hole could be lined with 203.2 mm casing.

Technical Requirement

The hole had to intersect a 5 m underground target at 656 m depth with accurate trajectory control.

Operational Requirement

Complete the hole efficiently in one pass while coordinating frequent surveys and adapting drilling parameters.

Operational Challenge

What made the project challenging

A large-diameter paste fill hole had to reach a small underground target without relying on the conventional multi-pass method.

Project Condition

The required diameter and casing were too large for a regular mineral exploration rig.

Technical Constraint

The hole needed to remain on trajectory and intersect a 5 m target deep in the underground development.

Operational Pressure

Surveying, bit changes and drilling parameters had to be coordinated as formations changed.

Boart Longyear Approach

How Boart Longyear approached the work

  1. Experienced Crews

    The crew mobilized and had the rig operational within one week, then completed the one-pass hole through changing formations.

  2. Method And Equipment Planning

    Boart Longyear selected a water-well-style rig with 130,000 lb pullback to accommodate the large-diameter casing and full 656 m depth.

  3. Equipment And Tooling

    A booster compressor and conventional DTH hammers supported cuttings removal; bits and hammers were changed as formations hardened.

  4. Safety Systems And Field Controls

    The program combined frequent surveying and controlled parameter changes; the client described the work as safe and accurate.

  5. Site Planning

    The hole was collared and cased in stages, reducing from 470 mm to 381 mm and then to the final 310 mm diameter.

  6. Technical Supervision

    Surtron Technologies and Boart Longyear completed regular multi-shot surveys and adjusted drilling parameters to keep the hole on trajectory.

  7. Regional And Field Support

    Boart Longyear coordinated with Surtron Technologies for specialist surveying throughout drilling.

  8. Execution Discipline

    Regular rod pulls supported bit inspection, replacement and surveying, with tooling adjusted as ground formations became harder.

  9. Quality / Project Outcome

    The 656 m hole reached the target in 39 12-hour shifts and intersected approximately 2.1 m from target center.

Outcome / Proof

What the work delivered

39 Shifts

Reached target in 39 12-hour shifts versus roughly 40–50 shifts expected with multi-pass methods.

2.1 m From Target Center

The 656 m hole intersected within approximately 2.1 m (6.9 ft) of the target center.

~$5M Future Gold Value per Level

The paste fill hole supports pillar extraction estimated to add about $5 million in gold value per mining level.

Why It Mattered

Impact

A one-pass directional approach reduced drilling time while delivering accurate paste-fill access for continued mining.

Related Capabilities

Services connected to this project

Let’s talk

Have a similar project requirement?

Talk with Boart Longyear about the method, equipment, and field support needed for your drilling program.