Case Study

Canadian Coring Program Averages 98.39% Core Recovery With Zero Re-Drills

Boart Longyear completed 218 holes and about 18,000 m of drilling for CNRL-Albian Sands while averaging 98.39% core recovery with zero re-drills and zero injuries.

Service
Surface Coring
Region
Canada
Application
Winter Drilling / Core Recovery
Project type
Mining

Executive snapshot

Client
Canadian Natural Resources
Service Used
Surface Coring
Operating Environment
Winter mine sites
Project Outcome
98.39% core recovery

Project Requirements

What the project required

Project Conditions

Complete a high-volume winter drilling program across Jackpine Mine and Muskeg River Mine.

Technical Requirement

Meet a contract requirement of at least 90% core recovery across the program.

Operational Requirement

Maintain productivity and safety despite winter crewing constraints and a compressed schedule.

Operational Challenge

What made the project challenging

A large winter coring program had to meet a demanding recovery requirement while staying ahead of schedule and budget.

Project Condition

The work covered 218 holes averaging 80 m each across two Canadian mine sites.

Technical Constraint

The contract required a minimum 90% core recovery with re-drills carrying added cost and schedule risk.

Operational Pressure

Tough winter conditions and crewing constraints increased pressure on schedule and execution.

Boart Longyear Approach

How Boart Longyear approached the work

  1. Experienced Crews

    Our experienced crews and work at the mine since 2002 were identified as key factors in completing the program with zero injuries and zero re-drills.

  2. Method And Equipment Planning

    The team completed 218 holes averaging 80.0 m and approximately 18,000 m in 60 days, working a 21-days-on / 7-days-off rotation.

  3. Equipment And Tooling

    The program used one LS250 Minisonic, three core rigs and one abandonment rig.

  4. Safety Systems And Field Controls

    Crews completed the winter program without injury while working through tight time restraints and difficult crewing conditions.

  5. Site Planning

    Work was coordinated across Jackpine Mine and Muskeg River Mine from January 2 to March 15, using a 21-days-on / 7-days-off rotation.

  6. Technical Supervision

    Performance was maintained against the 90% minimum recovery requirement, resulting in 98.39% average core recovery and zero re-drills.

  7. Regional And Field Support

    Multiple crews and a five-rig program supported drilling across both mine sites.

  8. Execution Discipline

    The team completed 218 holes in 60 days and achieved the project’s first year with zero re-drills.

  9. Quality / Project Outcome

    The program averaged 98.39% core recovery, completed approximately 18,000 m with zero injuries, and finished ahead of schedule and budget.

Outcome / Proof

What the work delivered

98.39% Core Recovery

Average recovery exceeded the 90% contract requirement, with zero re-drills.

~18,000 m in 60 Days

Crews completed 218 holes totaling about 18,000 m in approximately 60 days.

Zero Injuries

The program finished without injuries; the client also reported roughly 20% better cost efficiency than the prior year.

Why It Mattered

Impact

High recovery and no re-drills delivered substantial cost savings and helped the client finish ahead of schedule and budget.