Case Study
Canadian Coring Program Averages 98.39% Core Recovery With Zero Re-Drills
Boart Longyear completed 218 holes and about 18,000 m of drilling for CNRL-Albian Sands while averaging 98.39% core recovery with zero re-drills and zero injuries.
Executive snapshot
- Client
- Canadian Natural Resources
- Service Used
- Surface Coring
- Operating Environment
- Winter mine sites
- Project Outcome
- 98.39% core recovery
Project Requirements
What the project required
Project Conditions
Complete a high-volume winter drilling program across Jackpine Mine and Muskeg River Mine.
Technical Requirement
Meet a contract requirement of at least 90% core recovery across the program.
Operational Requirement
Maintain productivity and safety despite winter crewing constraints and a compressed schedule.
Operational Challenge
What made the project challenging
A large winter coring program had to meet a demanding recovery requirement while staying ahead of schedule and budget.
Project Condition
The work covered 218 holes averaging 80 m each across two Canadian mine sites.
Technical Constraint
The contract required a minimum 90% core recovery with re-drills carrying added cost and schedule risk.
Operational Pressure
Tough winter conditions and crewing constraints increased pressure on schedule and execution.
Boart Longyear Approach
How Boart Longyear approached the work
-
Experienced Crews
Our experienced crews and work at the mine since 2002 were identified as key factors in completing the program with zero injuries and zero re-drills.
-
Method And Equipment Planning
The team completed 218 holes averaging 80.0 m and approximately 18,000 m in 60 days, working a 21-days-on / 7-days-off rotation.
-
Equipment And Tooling
The program used one LS250 Minisonic, three core rigs and one abandonment rig.
-
Safety Systems And Field Controls
Crews completed the winter program without injury while working through tight time restraints and difficult crewing conditions.
-
Site Planning
Work was coordinated across Jackpine Mine and Muskeg River Mine from January 2 to March 15, using a 21-days-on / 7-days-off rotation.
-
Technical Supervision
Performance was maintained against the 90% minimum recovery requirement, resulting in 98.39% average core recovery and zero re-drills.
-
Regional And Field Support
Multiple crews and a five-rig program supported drilling across both mine sites.
-
Execution Discipline
The team completed 218 holes in 60 days and achieved the project’s first year with zero re-drills.
-
Quality / Project Outcome
The program averaged 98.39% core recovery, completed approximately 18,000 m with zero injuries, and finished ahead of schedule and budget.
Outcome / Proof
What the work delivered
98.39% Core Recovery
Average recovery exceeded the 90% contract requirement, with zero re-drills.
~18,000 m in 60 Days
Crews completed 218 holes totaling about 18,000 m in approximately 60 days.
Zero Injuries
The program finished without injuries; the client also reported roughly 20% better cost efficiency than the prior year.
Why It Mattered
Impact
High recovery and no re-drills delivered substantial cost savings and helped the client finish ahead of schedule and budget.
Related Capabilities
Services connected to this project
Surface Coring
Explore how this capability can support your drilling program.
Explore Surface Coring >Directional Drilling
Explore how this capability can support your drilling program.
Explore Directional Drilling >Reverse Circulation Drilling
Explore how this capability can support your drilling program.
Explore Reverse Circulation Drilling >Sonic Drilling
Explore how this capability can support your drilling program.
Explore Sonic Drilling >Let’s talk
Have a similar project requirement?
Talk with Boart Longyear about the method, equipment, and field support needed for your drilling program.