Case Study

Sonic Wells Recover 6,100 oz of Gold From a Heap Leach Pad

Boart Longyear used sonic sampling and targeted solution wells to identify and reactivate dry zones in a large Nevada heap leach pad, contributing to 6,100 ounces of recovered gold.

Service
Sonic Drilling
Region
USA
Application
Heap Leach Sampling / Solution-Well Installation
Project type
Mining
Status
Example / pending approval

Executive snapshot

Client
Nevada gold operation
Service Used
Sonic Drilling
Operating Environment
Heap leach pad
Project Outcome
6,100 oz recovered

Project Requirements

What the project required

Project Conditions

Identify dry zones created by compacted layers within a 400 ft heap leach pad.

Technical Requirement

Use continuous sonic cores to locate moisture and ore, then install targeted solution wells at the correct depths.

Operational Requirement

Work above the pad liner and cycle solution through multiple vertical zones without compromising the boreholes.

Operational Challenge

What made the project challenging

Compacted layers inside the heap leach pad were creating dry zones where leaching solution could not reach valuable mineralized material.

Project Condition

Repeated 50 ft lifts had compressed lower layers and created a dam effect within the pad.

Technical Constraint

The team needed accurate depth-based moisture and lithology information to target dry zones and exposed ore.

Operational Pressure

Solution wells had to stay intact while packers and screens were repositioned through repeated injection-and-rest cycles.

Boart Longyear Approach

How Boart Longyear approached the workThe Boart Longyear approach

  1. Experienced Crews

    Using the LS600 sonic rig, crews combined continuous core sampling with installation of targeted solution-enhancement wells in the 400-plus-foot heap leach pad.

  2. Method And Equipment Planning

    Test holes were drilled to 350 ft and stopped 50 to 75 ft above the liner; continuous cores identified the depths of dry zones, moisture and exposed ore.

  3. Equipment And Tooling

    The wells used 4.5-inch flush-threaded casing, upper and lower k-packers, and a 100-foot injection screen positioned between the packers.

  4. Safety Systems And Field Controls

    Test holes maintained 50 to 75 ft of clearance above the liner, while the flush-threaded casing kept each borehole intact during repeated well operations.

  5. Site Planning

    Sampling locations and well intervals were selected around the 50-foot lifts, compacted layers and dry zones identified from continuous cores.

  6. Technical Supervision

    Core information defined dry-zone depths, lithology, moisture concentration and exposed ore before solution intervals were positioned.

  7. Regional And Field Support

    Field teams repositioned the k-packers and injection screen so each well could deliver solution at bottom, middle and top intervals spanning 100 ft each.

  8. Execution Discipline

    Each interval followed an eight-week cycle of four weeks of solution and four weeks of rest before the packers and screen moved to a new depth.

  9. Quality / Project Outcome

    Over three years, 55 gravity-flow wells contributed to 6,100 oz of gold, approximately $8 million in value, 70-day payback and 400% IRR.

Outcome / Proof

What the work delivered

6,100 oz of Gold

The program contributed to recovery of 6,100 ounces of gold from the heap leach pad.

~$8M Value / 70-Day Payback

At the article's stated gold-price assumption, recovered gold equated to about $8 million and the project paid for itself within 70 days.

400% IRR

The client realized a reported 400% internal rate of return.

Why It Mattered

Impact

Targeted sonic sampling converted hidden dry zones into measurable recovery opportunities with rapid payback and strong return.

Related Capabilities

Services connected to this project

Let’s talk

Have a similar project requirement?

Talk with Boart Longyear about the method, equipment, and field support needed for your drilling program.